國慶中秋7天假,沒定單的正好可以藉此催單,有定單的,一定要安排好時間
下面轉(zhuǎn)篇放假通知范文供大家參考:
How are you?
We will have ***holiday from *** to ***.
Therefore we will be out of the office on ***to **on and return to work on ***.
If there are any orders during this period,pls try to release them before **(our production time will be *working days within these days), so that we can arrange the production before we take our holidays.
If there are any RFQs or some urgent things,pls try to send them before 16th,so that we can solve them timely.
For any further urgent needs, please send to mail xxxxx or call at 86-139 xxxxxx.
I'll have limited access to my mail, but will answer as soon as possible.
All other non PCB queries will be answered upon my return.
Thanks for your kind attention.
Best regards,
下面再轉(zhuǎn)篇L/C失敗案例,提醒下大家:
L/C收到時間:2007-12-3
最晚ETD:2008-1-30 (latest date of shippment)
到期日:2007-2-14 (Date of Expiry) in spain
貨值:USD40000.0
軟條款:Inspection Certificate issued by applicant or it's agency. (即客戶/客戶代理出具的驗貨報告)
分析:從上面可以看到,從收到L/C到ETD有59天,常規(guī)做貨時間45天。到期地點在客戶國家
結(jié)論:這是時間對于L/C來說是不太夠的,ETD=59天,ETC約=56,完成大貨時間=52,也就是說,在正常情況下45天完成大貨,還有52-45=7天的余地。也可以說還留有一班船的余地(就是說本周ETD若有問題,還可延至下周的ETD而不會導(dǎo)致不符點)
大家可以看到,這是一個特殊的時侯:春節(jié),所以接L/C的定單,有兩點要考慮:
1. 在L/C常規(guī)交貨期中要記得加15天左右的假期. 這樣既使無法在節(jié)前出貨, 過完節(jié)回來再出貨也不會有貨期不符點.因而過一個安心的年.
2. 貨期要相對常規(guī)貨期加長10天左右,因為工人會陸陸續(xù)續(xù)離開工廠,導(dǎo)致產(chǎn)量下降,或者供應(yīng)商延期交材料,甚至供應(yīng)商無法提供材料要換供應(yīng)商(我前天就接到通知說某個做紙箱的供應(yīng)商放假了,不接我們的單,因此,我的那個定單只能用倉庫的紙箱,因為沒有時間重新定料)!